Building Schedule for Hardware Upgrade


Work will take place between the hours of 10pm and 6am the following morning. No work will be done during the hours of 6am - 10pm. Additional Network upgrade dates are listed below.



Building Name Start Date End Date Completion Status
W.A. Baker Building - Chemistry Research July 5 July 8
Fine Arts Building July 5 July 13
NanoFab Facility July 10 July 14
E.E. Davis Hall July 13 July 25
Environmental Health & Safety July 17 July 17
Civil Engineering Lab Building July 18 July 19
Trinity House* July 20 July 20
Lipscomb* July 21 July 21
Kalpana Chawla House* July 24 July 24
Brazos House* July 25 July 25
Arbor Oaks* July 26 July 26
UTA - Fort Worth at Santa Fe Station July 26 July 28
Engineering Lab Building July 28 August 2
College Hall July 31 July 31
Engineering Research Building *DATE CHANGE* August 2 August 14
GeoScience Building *DATE CHANGE* August 14 August 16
UT Arlington Research Institute *DATE CHANGE* August 17 August 21
Maverick Activities Center *DATE CHANGE* August 22 August 28
Library *DATE CHANGE* August 21 August 25
Life Science Building *DATE CHANGE* August 23 September 9


* ResNet will not be affected by this change

These dates may change. Please check back as your building's scheduled date draws closer. 

 

Additional Network Upgrades

Date Start End Service(s) Affected
Sunday, July 30, 17              9 p.m.       3 a.m.        Campus-Wide, Intermittent Disruptions, UTA resources (ex. Faculty and Staff Email)