July Campus Parking & Roadway Construction
Monday, July 6, 2026
Parking and Transportation Services (PATS) is notifying the campus community of several planned parking lot and roadway improvement projects taking place throughout July. These projects are part of ongoing campus infrastructure improvements and may result in temporary parking restrictions, lane closures, and intermittent traffic delays.
Members of the campus community are encouraged to allow extra travel time and follow all posted signage and directions from construction personnel.
project schedule
Lot F12
- July 7: Demolition and base installation
- July 8: Curb and ADA ramp preparation and concrete pour
- July 10: Asphalt installation
- July 11: Sealcoat application (ADA section closed)
- July 13: Parking lot striping
Lot 27
- July 7: Saw cutting
- July 9: Asphalt repairs
Swift Center
- July 7: Saw cutting
- July 9: Asphalt repairs
South West Street & 4th Street
- July 7: Equipment delivery
- July 8: Cement stabilization
- July 9: Asphalt installation
Greek Row
Concrete Work
- July 9: Saw cutting
- July 13: Concrete demolition
- July 14–15: Site preparation
- July 16: Concrete pour
Roadway/Base & Asphalt Work
- July 20: Base stabilization
- July 22: Base stabilization
- July 23: Asphalt installation
- July 27: Asphalt installation
- July 28: Final striping
Lots F7 & 34
- July 27: Asphalt repairs
- July 28: Final striping
what to expect
- Temporary parking restrictions in affected lots
- Short-term roadway and pedestrian detours near active work zones
- Construction equipment and increased contractor activity
- Possible traffic delays during work hours
Construction schedules are weather dependent and may change if conditions require. Continue to monitor the PATS website and official university communications for project updates and any changes to parking or traffic impacts.


